Internet Installation Update (August 8, 2023)

By Karl Stephens
General Manager/COO

Despite the recent rain, Coastal Communications and its crews continue making progress with the fiber-to-the-home installation project. As a reminder, this is a 14-month project of building a fiber network to offer internet. You can contact Coastal Communications for more information (hello@coastal-comm.com).

Coastal Communications ended the week with 7,922 ft of production. The three missile crews worked South on Peregrine Crossing to Sorrelwood Crossing to Landings Way South then started on Landings Way South going North back to Peregrine Crossing. The drill crew continued work towards Green Island Road working on all of the tie-ins. This week, crews finished Section 1 on Landings Way South, including the culdesacs between Peregrine Crossing and Sorrelwood Crossing. They then moved on to Section 2, starting on Huntingwood Retreat and working South on Landings Way South to include Black Hawk Trail and all crossroads. The drill crew is still taking care of the tie-ins working back towards Green Island Road. Now that Coastal Communications has the permit for going under Green Island Road, they are waiting for the 811 locates for the same area. Crews should be clear to drill by August 21.

Some residents have asked how the fiber will be installed and what members can expect to see as the work unfolds. Below are some photos that explain the process, along with an example of a utility company marking its lines. As mentioned in previous Landings Association emails, advance crews have been marking utilities with paint and flags. This allows the subsequent boring crews to know where utilities are located when they install the conduit that will hold the new fiber. Please do not remove the flags. The crews will remove the flags when work is completed.

 

Access holes are dug approximately every 10 feet. This allows workers to guide the missile borer and helps locate items like irrigation systems that otherwise might not be marked.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Sod and dirt are set aside on a tarp to restore the landscaping after work is completed. In the second photo, you can see the white pipes of an irrigation system that were located and will be marked.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Pictured is the compressor to run the missile borer. A larger, directional borer will be used where appropriate on main thoroughfares.

 

 

 

 

 

 

 

 

 

Shown is the missile borer coming through the hole and being guided to the next hole.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Orange conduit is pulled through the hole created by the missile borer. It has a tracer wire with it for later locates as needed. Then, fiber cable will be “blown” through the conduit.

 

 

 

 

 

Shown is a junction box that will be installed flush to the ground. There is basically one box between each home. When homeowners sign up, crews can pull fiber from these boxes.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

These two photos show a splicing vault, where conduit from different runs will terminate, allowing the fiber to be connected. The vault has rocks inside to allow for better drainage. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

It is important that all utilities are located before work begins to avoid disruptions. This photo shows Utilities, Inc. of Georgia employees using ground penetrating radar and a pole to help find and mark its water lines.

 

 



This article was originally published by The Landings Association on their website.

Visit landings.org to read the original article.
https://landings.org/news/2023/08/08/internet-installation-update-august-8-2023