2021 Bridge Re-decking Project Update 

On Wednesday (April 14), Expert Marine Construction began re-decking the bridge that serves as a connector bridge for the residents between Paisley Court and Raindance Court. This community path bridge was re-decked in 2007 and has shown significant signs of deterioration over the last year. 

After Expert Marine removed the deck boards from the bridge, they discovered that the 72 stringers also required replacement, as they are splitting and broken off in several areas. Due to the additional work required, the bridge reopening is delayed. The bridge is anticipated to be completed by Monday, April 19

During this project, all residents must use the adjacent bridge between Tanaquay Court and Pine Shadow Court (please see the map below for the suggested alternate route or click here). 

Thank you in advance for your patience and support as we continue to improve the infrastructure located throughout the community. Should you have specific questions about the project, please contact The Landings Association’s Public Works Department (912-598-5509 or pwmanagers@landings.org).



This article was originally published by The Landings Association on their website.

Visit landings.org to read the original article.
https://landings.org/news/2021/04/16/2021-bridge-re-decking-project%C2%A0update%C2%A0